|
 |
|
|
|
Monash Interchange:
The showpiece of EastLink. This
impressive intersection links
the Monash Freeway and EastLink
through an intricate series of
steel and precast concrete
ramps and bridges.
The interchange required the
placement of 321 bridge beams
and the removal of 850,000 cubic
metres of earth.
The
Monash flyover or
steel box girder bridge stands
19 metres (more than 5 storeys)
above Eastlink.
This was one
of the largest projects
undertaken by our company and
involved over 2 years of work
for 22 members of staff at its
busiest.
|
 |
Deer Park Bypass:
The Deer Park Bypass
features four
lanes and four major
interchanges over its 10 km
length and opened to traffic in
early 2009 - 6 months ahead of
schedule. The project heavily
utilized machine control
guidance systems on numerous
graders, dozers and excavators.
The automatic guidance mode
eliminated operator error and
the need for re work. Several
guidance system manufacturers
were used making the job of
supporting and managing the
systems for our survey team all
the more challenging. |

 |
Westkon Precast Yard:
The new facility in Melton
produces super tee beams,
culverts and feature noise
walls. This new yard will
substantially increase Westkon's
production capacity.
Our scope of works included the
survey for the bulk earthworks
excavation of the site. The
setout of hundreds of piles as
well as the rail beams for the
massive overhead cranes.
|
.jpg)
.JPG) |
Geelong Road:
The
project
included the construction
of 8 Bridges, the increase of 36
kilometres of dual lane to a 3
lane freeway. Also, resurfacing
and widening the 14 kilometre
section between Werribee to the
Western Ring Road to 4 lanes.
The Geelong Road project
utilised one of the very first
grader machine control systems
to be used on a construction job
in Victoria. |
 |
|
|
|
Royal Melbourne Hospital:
Provided survey for the
construction of two new
buildings and a major series of
internal refurbishments in the
hospital. Work was undertaken
while normal hospital operations
continued A major
challenge was the lack of work
area to perform the required
surveying tasks. |

 |
Coode Island
Provided survey for Melbourne's
new hazardous chemicals storage
facility, thankfully equipped
with some of the world’s most
sophisticated safety and
environmental safeguards.
Located in the heart of
Australia’s busiest docklands
and yet only 500 metres from a
densely
populated residential area.
Provided setout for pipelines,
concrete bunds, associated
roadworks, pressurised, heated
and insulated storage tanks. The
11 tanks range in volume from
0.8 megalitres to 5.3 megalitres;
the latter having a diameter and
a
height of 20 metres. |
 |
Spencer Street Station
Provided surveying asbuilts of
the new stations main roof
trusses. Weighing up to 30
tonnes, the trusses were checked
at their fabrication sites
in Geelong and Launceston. Each
truss was transported
by barge. Placement was a
delicate manoeuvre and
had to be undertaken under
relatively calm weather
conditions. Also, work could not
start until the station closed
and had to be completed prior to
the first morning train.
Consequently a important part of
the process was our task of
verifying that each truss was as
per design. |
|
|
|
|